Before you begin integrating HitPay payments into your Ecwid store, you need to set up your HitPay account and ensure some prerequisites are met:
  1. If you haven’t already, create an account on HitPay.
  2. Ensure that you have the necessary payment methods activated in your HitPay account.
  3. In your HitPay dashboard, go to Integrations, open Ecwid and choose which payment methods show at checkout.

Integration Guide

Follow these steps to seamlessly integrate HitPay payments into your Ecwid store:
  1. Click on this link to add HitPay payment gateway to your Ecwid App

Install The Custom App

Ecwid Install
  1. Add the API Keys and Salt Values from HitPay in the fields below. You can find your API and Salt Keys by navigating to Developers > API and Salt Keys in the HitPay dashboard.
Ecwid Api
Please note that sandbox testing is not currently available on Ecwid.
  1. Click Save
Ecwid Save
  1. Enable/disable the payment methods for your Ecwid Checkout by updating your Ecwid integration settings in the HitPay dashboard (Integrations → Ecwid):
Ecwid Integration HitPay is now live on your Ecwid Store! 🎉

FAQs

No, HitPay does not send an email confirmation to your customer if the payment is made through Ecwid. This is because Ecwid, by default, sends an email to your customer with the order details. To avoid sending duplicate emails, HitPay does not send an additional email to your customers. As a merchant, you will receive a payment alert email.
On the HitPay checkout page, you will see the option for Apple Pay/Google Pay only once you select CARDS as the payment method. Additionally, it will work only if the browser supports the respective method:
  • Apple Pay: Only available on the Safari browser. Ensure you have Apple Pay enabled. Here's a guide from Apple on how to enable Apple Pay on your browser.
  • Google Pay: Only available on the Chrome browser. Ensure you have Google Pay enabled on your Google account.
Here are two checks you can perform to ensure the payment method is visible on your checkout page:
  1. Navigate to Payment Gateway > Integrations. Ensure that your payment method is enabled for your respective sales channel.
  2. If you have checkout rules, navigate to Payment Gateway > Checkout Customization > Payment Method Rules and ensure your payment method is selected.