Overview

Secure your HitPay account by enabling 2FA to provide an additional layer of security when logging in. Follow these steps to set up 2FA:
1

Access Security Settings

Click on Security from the top-right portion of the menu as shown below.
Security Menu
2

Enable 2FA

Click on “Set up two-factor authentication”.
3

Install Authenticator App

You will need to use any authenticator app such as Google Authenticator or Microsoft Authenticator available from the Apple App Store or Google Play Store. Follow the on-screen guide to proceed.
4

Scan QR Code

Scan the Barcode generated using your chosen Authenticator App and click Continue.
5

Verify Setup

Enter the code from your Authenticator App and Click Verify.
2FA Successfully Enabled
2FA is now activated! You will be prompted to enter a 2FA code from your authenticator app every time you log in to HitPay on the web and on mobile.